Controlling a Stage

From PRINCE2 Agile wiki
Jump to: navigation, search

Tailoring

It should be noted that PRINCE2 Agile stages, like PRINCE2 stages, are set based on the management perspective rather than delivery perspective used in releases and increments. That's why stages are not considered the same as any of those concepts.

A PRINCE2 Agile stage contains one or more releases, and each release contains one or more iterations (Sprints in Scrum).

Stage, release, sprint.png

Based on this arrangement, the Controlling a Stage process won't have much differences with the original process.

Notable differences:

Each Work Package would describe multiple releases and iterations, and would be broken down and elaborated into release plans and iteration plans based on the Agile framework in use at the delivery level.

Process Model

PRINCE2 Agile Process Model state06.png

Legend:

Notes:

  • The above image assumes that Scrum is used in the delivery level, which is not necessary.
  • The number of stages, releases, and Sprints are just examples, as well as the exception in the third stage.
  • The diagram is schematic and many details are not shown.